Road work shapes daily life in Estero more than almost anything else: how long the drive to I-75 takes, which entrance you use to get home, and what a street will look like in three years. This page tracks the road and traffic projects in and around the Village of Estero, what stage each one is in, and the completion dates the responsible agency has published. Every source listed below was checked on November 3, 2026. Where an agency has not published a completion date, we say so instead of guessing. We update this page as agencies post new information.
Three agencies build roads here. The Village of Estero handles local streets, intersections and pathways inside the Village. Lee County DOT handles county roads such as Corkscrew Road east of I-75 and Three Oaks Parkway. The Florida Department of Transportation (FDOT) District One handles I-75 and US 41. For parks, municipal buildings and other non-road Village work, see our Village of Estero projects 2026-2027 page.
Summary Table: Estero Road Projects (Checked November 3, 2026)
| Project | Limits | Status | Expected completion | Source |
|---|---|---|---|---|
| I-75 widening, express and auxiliary lanes (FDOT 452544-1) | North of Golden Gate Pkwy (Collier) to south of Alico Rd (Lee), about 21 miles | Design-build contract executed Jan. 16, 2026; FDOT fact sheet lists construction phase, start mid-2026 | Overall date not published; FDOT official cited a three-year timeframe and early 2027 for the Bonita Beach Rd to Immokalee Rd relief lanes | SWFLRoads fact sheet; FDOT D1 design-build page; WGCU, Sept. 20, 2026 |
| Corkscrew Road widening, Phase 2 (Lee County) | Bella Terra Blvd to just east of Alico Rd | Under construction since early 2024 | End of 2026 | Lee County update via Village of Estero, June 5, 2026; Lee County Roadwatch, July 16, 2026 |
| Corkscrew Road widening, Phase 1 (Lee County) | Ben Hill Griffin Pkwy to Bella Terra Blvd | Complete | Complete | WINK News, Aug. 26, 2025; corkscrewroadwidening.com |
| Corkscrew Road shared use path (Village of Estero) | North side of Corkscrew Rd at Ben Hill Griffin Pkwy area | Under construction (sod and finish work in July 2026) | Fall 2026 | Lee County Roadwatch, July 16, 2026 |
| Three Oaks Parkway extension, Phases 1 and 2 (Lee County) | North of Alico Rd to Daniels Pkwy | New roadway opened after Nov. 2, 2026 ribbon cutting; work continues | Final completion early 2027 | WGCU, Oct. 29, 2026 |
| I-75 at Daniels Pkwy (Exit 131) diverging diamond (FDOT) | I-75/Daniels Pkwy interchange | Under construction since January 2026 | Summer 2028 | WGCU, Jan. 10, 2026; Lee County Roadwatch, July 16, 2026 |
| Williams Road widening (Village) | US 41 to Via Coconut Point, 2 to 4 lanes | Planned; $90,000 scheduled in FY 2026-27 of a $6.8M estimate | Not published | Village CIP, May 14, 2026 |
| Williams Rd at Atlantic Gulf Blvd intersection (Village) | Williams Rd just west of US 41 | Funded in FY 2026-27 and FY 2027-28 | Not published | Village CIP, May 14, 2026 |
| US 41 at Pelican Colony Blvd traffic signal | US 41 at Pelican Colony Blvd | Developer funding scheduled FY 2026-27 | Not published | Village CIP, May 14, 2026 |
| Broadway Avenue West safety and drainage (Village) | Broadway Ave W, west of US 41 | Design phase through October 2026; no construction underway | Not published | Village of Estero project page, June 2026; Village CIP, May 14, 2026 |
| Sandy Lane bike/ped improvements (Village) | Sandy Lane corridor | Postponed; removed from CIP after state funding ended | None | Village Council action, June 17, 2026 |
| US 41 at Bonita Beach Rd (FDOT PD&E study) | US 41/Bonita Beach Rd intersection, Bonita Springs | Design concept accepted July 25, 2025 | No construction date published | FDOT Newsletter #4, Aug. 2025 |
I-75: Widening Through Estero
FDOT’s largest local project is the I-75 widening listed on SWFLRoads as project 452544-1, running from north of Golden Gate Parkway in Collier County to south of Alico Road in Lee County, about 21 miles. FDOT describes the work as auxiliary lanes and express lanes in both directions, a new diverging diamond interchange at Immokalee Road, ramp changes at key interchanges, resurfacing, and noise walls where warranted. The fact sheet lists the project in the construction phase with a mid-2026 start but does not publish a completion date.
FDOT’s District One design-build page shows the contract for “I-75 from N of Golden Gate to S of Corkscrew” (FPID 452544-1) awarded to de Moya Leware Joint Venture II, executed January 16, 2026. FDOT’s older Moving Florida Forward page still lists a 2027 construction start and $578 million in funding for the Golden Gate to Corkscrew segment, so the agency’s own pages do not fully agree on timing.
WGCU reported on September 20, 2026 that work was slated to begin in fall 2026, with two optional toll express lanes in each direction from Golden Gate Parkway to Corkscrew Road and one through the Corkscrew Road interchange. An FDOT official gave an early 2027 timeline for the congestion relief lanes between Bonita Beach Road and Immokalee Road and a three-year construction window overall. The same report said FDOT plans about 16 miles of 22-foot noise walls serving 29 neighborhoods, and that FDOT’s map showed no continuous wall along The Brooks in Estero.
For drivers: the FDOT fact sheet did not list a lane closure schedule when we checked. For the nearby Daniels Parkway job, FDOT and Lee County use overnight I-75 closures, so check FL511 before late-night trips on I-75 between Bonita Beach Road and Alico Road.
I-75 at Daniels Parkway (Exit 131)
North of Estero, FDOT and Lee County are rebuilding the Daniels Parkway interchange as a diverging diamond. Construction began in January 2026, the cost is about $43 million, and completion is expected around summer 2028. Lee County lists I-75 lane closures from 9 p.m. to 7 a.m. when needed, and WGCU reported Daniels Parkway closures from 8 p.m. to 7 a.m. This matters to Estero residents who use Exit 131 for the airport or JetBlue Park.
Corkscrew Road
Lee County’s Corkscrew Road widening covers 4.4 miles from Ben Hill Griffin Parkway to Alico Road. Phase 1, from Ben Hill Griffin to Bella Terra Boulevard, is finished; it provides six lanes to Fire House Lane and four lanes from there to Bella Terra. Phase 2 builds four 11-foot lanes from Bella Terra Boulevard to just east of Alico Road and adds a traffic signal at Alico Road. Lee County’s June 5, 2026 update, posted by the Village, set completion at the end of 2026, citing extra Lee County Utilities work and utility relocations by FPL and Lumen. That update also announced a traffic shift onto the new south-side lanes and night drainage work from 7 p.m. to 5 a.m. The Village posted a newer Lee County update on October 16, 2026; check the Village news page for its details.
The Village’s own 10-foot asphalt shared use path along the north side of Corkscrew Road, in the Ben Hill Griffin area, had an estimated completion of fall 2026 in the July 16, 2026 Roadwatch, with lane closures from 8 a.m. to 3:30 p.m. for sod work. The Village’s May 2026 CIP document lists $1.3 million in the FY 2026-27 column for a turn lane at Stoneybrook Golf Boulevard and Corkscrew Road; the same document also lists the project in its “not in 5-year CIP” table, so check the adopted budget for its final status.
East of Alico Road toward Verdana Village and Kingston, no construction is scheduled. Engage Estero reported in June 2026 that it asked county commissioners to fund the next study phase. Buyers comparing the two newest Corkscrew communities can read our Kingston vs. Verdana Village comparison.
Three Oaks Parkway Extension
Lee County held a ribbon cutting on November 2, 2026 at Three Oaks Parkway and Fiddlesticks Boulevard to open the new extension north of Alico Road. Phase 1 runs from north of Alico Road to the Fiddlesticks Canal near Indian Paint Lane (about $26.8 million, Wright Construction Group). Phase 2 runs from Indian Paint Lane to Daniels Parkway (about $39.7 million, ECH Construction). Both are four lanes with bike lanes and sidewalks. Final completion is scheduled for early 2027, ahead of the mid-2028 date the county had listed earlier. For Estero drivers, the extension gives a north-south route parallel to I-75 and US 41 between Corkscrew Road and Daniels Parkway.
US 41, Williams Road and Village Intersections
The Village’s five-year Capital Improvement Plan for FY 2026-27 through FY 2030-31, dated May 14, 2026, is the best published guide to local road work. Funded items include:
- Williams Road at Atlantic Gulf Boulevard: $3.27 million, funded across FY 2026-27 and FY 2027-28. Earlier Village design materials describe closing the median at Atlantic Gulf and adding bike lanes, sidewalks and crosswalks.
- River Ranch Road turn lanes at Williams Road and pedestrian crossings: $1.35 million in FY 2026-27.
- US 41 at Pelican Colony Boulevard signal: $1.1 million in developer funding in FY 2026-27.
- Developer-funded signals: US 41 at Via Rapallo/Fountain Lakes (FY 2027-28 to 2028-29), Wildcat Run (FY 2027-28) and WildBlue/River Creek (FY 2028-29).
- Estero Parkway at US 41 turn lanes: $350,000 in FY 2027-28 toward a $3.2 million estimate.
- Via Coconut Point: $650,000 for the railroad crossing and FDOT-supported roundabout improvements in FY 2026-27 and FY 2027-28.
- Coconut Road sidewalk, Oakwilde to Via Coconut Point: FDOT funding in FY 2026-27 and FY 2027-28.
Williams Road widening from US 41 to Via Coconut Point carries a $6.8 million estimate but only $90,000 scheduled, in FY 2026-27, so construction funding does not appear in the five-year window. The Coconut Road roundabouts at Meadowbrook and El Dorado, US 41 at Pelican Sound, and the Corkscrew Road and Three Oaks Parkway intersection are listed without scheduled funding. The CIP places widenings of Ben Hill Griffin Parkway, Three Oaks Parkway and Corkscrew Road under Lee County, with no cost or year. We found no published construction schedule for a southern extension of Via Coconut Point.
Engage Estero reported that a protected left-turn signal was installed at US 41 and Williams Road in late May 2026. Lee County’s July 2026 Roadwatch also listed a temporary closure of northbound Via Coconut Point at Williams Road through July 27, 2026, with US 41 and Three Oaks Parkway as detours.
Broadway, Sandy Lane and Trails
Broadway Avenue West, west of US 41, is in design for safety, drainage and pedestrian work, with the design phase running through October 2026 and no construction underway, per the Village’s project page. The May 2026 CIP shows $12.5 million for Broadway West, largely offset by grants. On June 17, 2026, the Village Council adopted a resolution postponing Sandy Lane bike and pedestrian improvements and removing the project from the CIP after state funding ended. On October 28, 2026, the Council voted to continue with its share of the 11.4-mile Bonita Estero Rail Trail; WGCU reported that the right-of-way closing is scheduled for January and construction is at least two years away.
How to Check Live Closures
- FL511: FDOT’s statewide traveler site and app show real-time incidents, closures and cameras on I-75 and US 41.
- SWFLRoads.com: FDOT District One’s project site, with fact sheets, contacts and weekly District One Roadwatch notices.
- Lee County DOT Roadwatch: a weekly report of county lane closures, including Corkscrew Road, Three Oaks Parkway and Village projects.
- Village of Estero news: posts Lee County’s Corkscrew Road updates and Village project notices.
What It Means for Homebuyers
Commute: The largest active projects near Estero are on Corkscrew Road and I-75. Corkscrew Phase 2 is scheduled to finish at the end of 2026, while I-75 work between Bonita Beach Road and Corkscrew Road is beginning. If you are looking at homes east of I-75, ask your agent to time a test drive at your normal commute hour, and check FL511 before you go.
Noise: Homes that back up to I-75 may be affected by both construction noise and the future wider highway. FDOT’s planned noise walls reduce but do not eliminate traffic noise, according to FDOT’s own comments to WGCU. Whether a wall is planned for a particular neighborhood is something to confirm on FDOT’s project maps before you buy. Buyers looking at The Brooks or other communities along the interstate should look at this closely.
Future access: New signals and turn lanes in the CIP can change how you enter and leave a neighborhood. Funded items such as the WildBlue/River Creek and Wildcat Run signals have fiscal years attached; unfunded ones may never be built. Treat anything without scheduled funding as uncertain.
To compare neighborhoods by location, start with our Estero gated communities guide, browse Estero homes for sale, and review new building activity on our Estero developments 2026-2027 page.
For new apartments, shopping centers, parks and other projects, see our Estero development tracker.
Frequently Asked Questions
When will the Corkscrew Road widening be finished?
Phase 1, from Ben Hill Griffin Parkway to Bella Terra Boulevard, is complete. Lee County expects Phase 2, from Bella Terra Boulevard to just east of Alico Road, to be complete at the end of 2026, per its June 5, 2026 update.
Is I-75 being widened through Estero?
Yes. FDOT’s project 452544-1 adds auxiliary and express lanes from north of Golden Gate Parkway to south of Alico Road. The design-build contract was executed January 16, 2026, and FDOT has not published an overall completion date.
Is the Three Oaks Parkway extension open?
Lee County opened the new extension after a ribbon cutting on November 2, 2026. Work continues in the area, and final completion is scheduled for early 2027.
When will Williams Road be widened to four lanes?
No construction date is published. The Village’s May 2026 CIP lists a $6.8 million estimate for Williams Road from US 41 to Via Coconut Point, with only $90,000 scheduled in FY 2026-27.
Where can I check road closures before I drive?
Use FL511 for real-time conditions on I-75 and US 41, SWFLRoads.com for FDOT project notices, and Lee County DOT’s weekly Roadwatch report for county road closures.
Sources
All sources checked November 3, 2026.
- FDOT SWFLRoads: I-75 from Golden Gate Parkway to Alico Road (452544-1) fact sheet
- FDOT District One design-build projects (contract E1Y26)
- FDOT Moving Florida Forward: I-75 Golden Gate Parkway to Corkscrew Road
- WGCU, Sept. 20, 2026: I-75 improvement project to begin this fall
- WGCU, Jan. 10, 2026: Daniels Parkway diverging diamond begins
- Lee County DOT Roadwatch, July 16-22, 2026
- Village of Estero: Corkscrew Road Widening Phase 2 update, June 5, 2026
- Village of Estero: Corkscrew Road Widening Phase 2 update, Oct. 16, 2026
- Lee County Corkscrew Road Widening project site
- WINK News, Aug. 26, 2025: Corkscrew widening status
- WGCU, Oct. 29, 2026: Three Oaks Parkway ribbon cutting Nov. 2
- Village of Estero 5-Year CIP, FY 2026-27 to 2030-31 (May 14, 2026)
- Village of Estero Capital Improvement Projects
- Village of Estero: Broadway Avenue West Safety and Drainage Project
- Village of Estero: Council actions, June 17, 2026
- FDOT: US 41 at Bonita Beach Road PD&E Newsletter #4 (Aug. 2025)
- Engage Estero, June 18, 2026: first six months of 2026
- WGCU, Oct. 29, 2026: Estero council moves ahead with rail trail
- FL511 traveler information
- SWFLRoads.com (FDOT District One)
- Lee County Transportation