Estero Development Tracker: New Apartments, Shops, Parks and Roads
Estero is changing fast. Apartments are going up along US 41 and Corkscrew Road, the Village is building a 100-acre sports park and a riverfront park, and thousands of new homes are planned east of I-75. If you live here or are thinking about buying, these projects shape traffic, views, schools, home values and what you will be able to walk or drive to in a few years.
This tracker lists the major residential, commercial, public and road projects in and around the Village of Estero, with the most recent dated action we could verify and a link to the source. It was last checked in November 2026. Projects move through several public steps before anything is built, so a “proposed” project may change a lot or never happen.
Estero Development at a Glance
| Project | Type | Where | Size | Latest status |
|---|---|---|---|---|
| Woodfield Estero | Mixed use | US 41 and Coconut Rd (former Lee Health land) | 600 apartments planned, 190-room hotel, retail and office | Phase 1 under construction; first units expected Q3 2027 |
| Lumio (Via Coconut) | Apartments + retail | Via Coconut Point and Corkscrew Rd | 330 apartments, commercial space, 1-acre public park | Under construction; completion targeted end of 2026 |
| Broadway & US 41 | Residential | US 41 north of Broadway | About 310 homes in three mid-rise buildings plus townhomes | Land cleared 2025; first building estimated 2027 |
| Waypoint at Coconut Point | Apartments (proposed) | Former Regal theater site, Coconut Point | 362 apartments plus garage | Planning board workshop Mar 10, 2026; no vote |
| TRG Estero | Apartments + retail (proposed) | Estero Pkwy and Three Oaks Pkwy | Up to 370 apartments, 33,000 sq ft retail | Public information meeting May 19, 2026; no application filed as of May |
| Brooks Town Center Apartments | Apartments | Three Oaks Pkwy and Coconut Rd | 137 units, four stories | Completion expected fall 2026 |
| Summercrest by Toll Brothers | Townhomes | Corkscrew Rd and Sandy Ln | Up to 154 townhomes | Opened Sept 18, 2026 |
| Mission Grove of Estero | Senior living (proposed) | Corkscrew Rd and Three Oaks Pkwy | 163 independent, assisted and memory care units | Public information meeting July 21, 2026 |
| The Island at West Bay Club | Condo tower | West Bay Club | 24 stories, 86 residences | Under construction |
| Estero Crossing and Corsa | Retail + apartments | Corkscrew Rd between Three Oaks Pkwy and I-75 | 306 apartments plus retail | Under construction |
| Home2 Suites at Coconut Point | Hotel | Coconut Point | 111 rooms | Zoning approved July 2, 2025 |
| Corkscrew Village self-storage | Commercial | 8900 Commons Way | 75,910 sq ft | Approved May 19, 2026 |
| Henning Design Center | Commercial | US 41 south of Broadway | 16,000 sq ft | Planning board recommended approval May 19, 2026 |
| Estero Fire Rescue expansion | Public safety | Three Oaks Pkwy south of Corkscrew Rd | Storage building and station addition | Rezoning approved June 3, 2026 |
| Southwest Florida Proton Center | Medical | Estero Pkwy and Three Oaks Pkwy | 35,000 sq ft | Opened December 2025 |
| Estero SportsPark | Village park | Williams Rd | Nearly 100 acres, built in phases | Phase 1 under construction |
| High 5 Entertainment | Entertainment | Williams Rd east of Via Coconut Point | Pickleball, bowling, mini golf, restaurant | Under construction; opening dates have shifted |
| Estero RiverPark | Village park | US 41 and Corkscrew Rd | 62–64 acres on the Estero River | Phase 1 parking finished May 2026 |
| Bonita Estero Rail Trail | Trail | Seminole Gulf rail corridor | Regional rail-trail | Bonita referendum passed Aug 18, 2026 |
| Three Oaks Pkwy stormwater park | Flood control | Three Oaks Pkwy | 69 acres | In design; must finish by Mar 31, 2027 |
| Broadway Ave West septic-to-sewer | Utility | West of US 41 | About $20.3 million | Approved June 17, 2026 |
| Corkscrew Rd widening, Phase 2 | Road (Lee County) | Bella Terra Blvd to east of Alico Rd | Four lanes | Completion expected end of 2026 |
| Kingston | Master-planned community | East Corkscrew Rd | About 10,000 residences planned | Broke ground Nov 13, 2025 |
| Corkscrew Grove East Village | Master-planned community (Collier) | Lee–Collier–Hendry line | Up to 4,502 homes | Collier approval Apr 28, 2026 |
Last checked November 2026. Status is the latest dated action we found in Village of Estero meeting summaries, county reports, developer announcements and news coverage. See each section below for sources.
How a Project Gets Approved in Estero
Most private projects inside the Village go through the Planning, Zoning and Design Board (PZDB), which often holds a public information meeting first with no vote. Rezonings then go to the Village Council, which makes the final decision by ordinance at public hearings. Development orders and design approvals can be handled at the PZDB level. Agendas and meeting summaries are posted on the Village of Estero agendas page, and anyone can speak during public comment.
Projects east of the Village limits, such as Kingston and the Corkscrew Road widening, are handled by Lee County. Corkscrew Grove East Village is in Collier County.
Apartments and New Homes
Woodfield Estero
The largest mixed-use project inside the Village, on the former Lee Health land at the northwest corner of US 41 and Coconut Road, across from Coconut Point. FRP Development and Woodfield Development plan 600 apartments, a boutique hotel of about 190 rooms, about 80,000 square feet of retail and 20,000 square feet of office space on roughly 45 acres. Business Observer reported in September 2026 that Phase 1 (296 apartments) was under construction with an $81.5 million construction loan and that the first units are expected in the third quarter of 2027. The Village Council approved the rezoning in July 2023.
Lumio at Via Coconut
A 330-unit rental community with ground-floor commercial space on about 20 acres at the southwest corner of Via Coconut Point and Corkscrew Road, across from Genova. The plan includes a 1-acre public park donated to the Village. Engage Estero’s first-quarter 2026 community report put completion at the end of 2026.
Broadway and US 41
About 310 homes in three mid-rise buildings plus townhomes on 34 acres along US 41 just north of Broadway, with some commercial space. The development order was approved in April 2023, the land was cleared in 2025, and the first building was estimated for 2027. Sources disagree on the builder.
Waypoint at Coconut Point (proposed)
Simon Property Group’s proposal to replace the closed Regal theater and part of its parking at Coconut Point with apartments and a parking garage. The plan dropped from 365 to 362 units between a January 2026 public information meeting and a March 10, 2026 workshop, where the planning board suggested revisions. No vote had been taken in the summaries we found. Engage Estero has publicly opposed it.
TRG Estero (proposed)
The Residential Group presented plans for up to 370 apartments and 33,000 square feet of retail on 31 acres at the southwest corner of Estero Parkway and Three Oaks Parkway, near FGCU and Rookery Pointe. The May 19, 2026 meeting was informational only. WGCU reported that Rookery Pointe residents raised flooding and traffic concerns and that no formal application had been filed as of late May.
Other residential projects
- Brooks Town Center Apartments: 137 units in one four-story building on the former Winn-Dixie site at Three Oaks Parkway and Coconut Road, expected to finish in fall 2026.
- Summercrest by Toll Brothers: up to 154 two-story townhomes at Corkscrew Road and Sandy Lane. The community and sales center opened on September 18, 2026, with homes priced from the mid-$500,000s according to Toll Brothers. See our Summercrest guide.
- Mission Grove of Estero (proposed): 163 independent living, assisted living and memory care units in three-story buildings at Plaza del Sol, presented to the planning board on July 21, 2026.
- The Island at West Bay Club: Kolter Urban’s 24-story tower with 86 condominiums inside West Bay Club, under construction. See our West Bay Club guide.
- Corsa at Estero Crossing: 306 apartments in STOCK Development’s Estero Crossing project on Corkscrew Road west of I-75.
Shopping, Hotels and Offices
- Estero Crossing: STOCK Development’s retail center on the south side of Corkscrew Road between Three Oaks Parkway and I-75. STOCK lists tenants including Chicken Salad Chick, Crisp & Green, Oak & Stone, Orangetheory and The Joint.
- Coconut Point refresh: the planning board approved new building colors, a new logo and sign changes for the mall on July 21, 2026.
- Home2 Suites by Hilton: a four-story, 111-room hotel behind Coconut Point, approved by the Village Council on July 2, 2025.
- Other approved hotels: Engage Estero’s report lists an extended-stay hotel on Lynden Drive, a Hilton Garden Inn on Sweetwater Ranch Boulevard and a Holiday Inn on US 41, none with confirmed construction as of early 2026.
- Corkscrew Road corridor: a Chick-fil-A at Ben Hill Griffin Parkway, an Aldi on Newbridge Drive and a medical office building were in design or review in early 2026.
- Corkscrew Village self-storage: a 75,910-square-foot expansion behind the Publix center, approved May 19, 2026.
- Henning Design Center: a 16,000-square-foot building on US 41 south of Broadway; the planning board recommended approval on May 19, 2026.
Medical and Public Safety
- Southwest Florida Proton Center opened in December 2025 at Estero Parkway and Three Oaks Parkway, according to Engage Estero’s report.
- HCA land on US 41 at Williams Road: about 100 acres bought for a possible hospital in 2019. As of early 2026 there was no approved plan.
- Estero Fire Rescue got Council approval on June 3, 2026 to rezone its Three Oaks Parkway site for a storage building and a station addition.
Village Parks and Capital Projects
The Village’s 2026–27 capital improvement program totals about $75.9 million, with most of it going to parks and land, according to the Village and Engage Estero.
- Estero SportsPark: a park of nearly 100 acres on Williams Road between Via Coconut Point and Estero High School, built in phases. Phase 1 includes practice fields, a central lake and utilities. In July 2026 the Council postponed design of later phases until construction money is available.
- High 5 Entertainment: a private venue next to the SportsPark with pickleball, bowling, mini golf and a restaurant. It broke ground on November 14, 2025. Opening dates have shifted, and a June 2026 Council workshop described a grand opening around late February or early March.
- Estero RiverPark: 62 to 64 acres at US 41 and Corkscrew Road on the Estero River, formerly called Estero on the River. About 30 acres are protected preserve, and Phase 1 parking was finished in May 2026. Options for the north side, including a public-private partnership, were still under discussion in mid-2026.
- Bonita Estero Rail Trail: a planned trail on the Seminole Gulf rail corridor through Bonita Springs and Estero. Estero approved a purchase agreement in March 2026, and Bonita Springs voters approved a bond referendum on August 18, 2026.
- Three Oaks Parkway stormwater park: a 69-acre site behind the post office that the Village is designing to reduce flooding along the North Branch of the Estero River, with FEMA grant money.
- Broadway Avenue West septic-to-sewer: a roughly $20.3 million project, mostly FEMA-funded, to connect Estero River Heights, Cranbrook Harbor and nearby neighborhoods to sewer, adopted June 17, 2026.
Road projects such as the I-75 widening and Corkscrew Road work are covered in more detail in our Estero road construction updates.
Just Outside the Village
- Corkscrew Road widening, Phase 2: Lee County is widening Corkscrew Road to four lanes from Bella Terra Boulevard to just east of Alico Road. The county’s August 2026 Road Watch report expected completion at the end of 2026.
- Kingston: Cameratta Companies’ master-planned community on East Corkscrew Road, with about 10,000 residences planned. It broke ground on November 13, 2025 with Lennar, Neal, Pulte, Taylor Morrison and Kolter. See our Kingston guide.
- Corkscrew Grove East Village: Alico’s plan for up to 4,502 homes on former citrus land in Collier County, unanimously approved by the Collier County Commission on April 28, 2026. Its traffic will use Corkscrew Road.
- The Pandion Club: a private golf club redevelopment on East Corkscrew Road that Engage Estero reported was planned to open in fall 2027.
What This Means If You Are Buying or Selling
- Check what is planned next to the home. A vacant parcel behind a house can become apartments or a shopping center. Ask the Village or look up the parcel’s zoning before you buy.
- Expect more traffic on Corkscrew Road and US 41 as Kingston, Corkscrew Grove and the US 41 apartment projects fill in.
- Amenities are coming. The SportsPark, RiverPark, rail trail and new restaurants and shops can make nearby neighborhoods more convenient.
- More rentals. Several hundred new apartments will give renters more choices and may affect rents and investor returns in some neighborhoods.
Thinking about how a nearby project could affect a home you own or want to buy? Call The DiBe Group at 239-256-5005. You can also see our Estero community comparison and Estero permits guide.
Frequently Asked Questions
What is being built in Estero, Florida?
Major projects include Woodfield Estero (600 apartments, a hotel and retail at US 41 and Coconut Road), Lumio (330 apartments at Via Coconut Point and Corkscrew Road), about 310 homes at Broadway and US 41, the Village’s Estero SportsPark and RiverPark, and the Kingston community on East Corkscrew Road.
Are apartments being built at Coconut Point?
Simon Property Group has proposed Waypoint, about 362 apartments and a parking garage on the former Regal theater site. As of the summaries we found, the planning board had held a workshop in March 2026 and suggested revisions, with no vote.
When will the Estero SportsPark open?
The Village is building the SportsPark in phases on Williams Road. Phase 1 (practice fields, a lake and utilities) was under construction in 2026. Check the Village of Estero website for current opening dates.
When will Corkscrew Road widening be finished?
Lee County’s August 2026 Road Watch report expected Phase 2 of the Corkscrew Road widening, from Bella Terra Boulevard to east of Alico Road, to be finished at the end of 2026.
How can I find out what is planned near a home in Estero?
Check the Village of Estero agendas page for Planning, Zoning and Design Board and Council items, look up the parcel’s zoning, and ask a local agent. For homes east of the Village, check Lee County’s zoning records.
Sources
- Village of Estero: Agendas and minutes
- Business Observer: Woodfield Estero underway (Sept 10, 2026)
- Engage Estero: Greater Estero Community Report, Q1 2026 (resident advocacy group)
- Village of Estero: Planning board, March 10, 2026
- Village of Estero: Planning board, May 19, 2026
- WGCU: TRG Estero plans (May 22, 2026)
- Village of Estero: Planning board, July 21, 2026
- Toll Brothers: Summercrest now open
- Village of Estero: Council, June 17, 2026
- Village of Estero: Council, June 3, 2026
- WGCU: Bonita Estero Rail Trail referendum
- Lee County DOT: Road Watch, August 2026
- WGCU: Kingston groundbreaking
- WGCU: Corkscrew Grove East Village approval
- STOCK Development: Estero Crossing
- Gulfshore Business: Home2 Suites at Coconut Point